Now beginning to look like something. And hey, I didn’t have an 11-1/2 foot tall 2x6 wall pin me underneath it yet. Now to get the ceiling joists, decking, and two engineered beams ordered and in here before the flooding rains soften up the driveway too much for an 18 wheeler.
Attachments
It WAS raining this morning when they dropped the batch off. The lam beams are coming early next week. They can bring those in on the smaller truck. The stack of PT is for another project - just made sense to get it all at once.
Attachments
Got this milestone out of the way today. Had to walk that sucker up on speaker cabs, with some safety rigging in place. Now I can finish the beams for all the flat ceiling, and floor of the attic storage room.
The bigger one (26 ft) at the center of the vaulted ceiling is going to take some rental equipment. Got 2 grand in the budget for the rent. Need some hydraulics. Plenty of work to do in the meantime.
The bigger one (26 ft) at the center of the vaulted ceiling is going to take some rental equipment. Got 2 grand in the budget for the rent. Need some hydraulics. Plenty of work to do in the meantime.